Stage: 4. Project implementation
Implementing Authority
Klaipeda district municipality administration
Partnership form
Public-Private Partnership
Duration
15 years
Value
18 463 949 Eur (inc. VAT) net present value
Private investment
13 971 186 Eur (inc. VAT) real value
Partner selection form
Competitive Dialogue
Private partner
UAB "Sip2" and UAB "Sip3"
Contract signature date
2022 10 21
The date of full entry into force of the contract
2023-04-18
Transmitted activities
Design, construction, operation, maintenance, provision of commercial services (infrastructure rental) and other services
Description:
Design, construction, maintenance and other services of multifunctional center with a total building area of up to 8,500 m2., located in Sendvaris eldership of Klaipėda district municipality, Trušelių village, Agilos str. 12. The multifunctional center will be dedicated to pre-school education (230 places), primary education (550 places), sports services infrastructure, cultural services infrastructure, outdoor playgrounds and sports grounds, parking, paths, greenery, etc.
Area: Educational system, Culture, sports, leisure facilities
Current situation
- Summary PPP Risk Assessement for inclusion in the national financial statement can be found here (98.2 KB ).
- On 18 April 2023 the contract entered into force.
- On 21 October 2022 a contract was concluded.
- On 21 June 2021 completed evaluation of the applications, initial proposals from 4 candidates are expected.
- On 6 March 2021 Klaipėda district municipality published procurement documents (announcement).
- On 8 February 2021 the second public presentation represented their project and discussion for interested business representatives, concerning procurement documents (public presentation (669 KB )).
- Short video about of the public private partnership (video).
- On 9 November 2020 the firs public consultation represented their project and discussion for interested business representatives (public presentation (1.1 MB ) (1.5 MB )).
- On 1 October 2020 Central Project Management Agency evaluated socio-economic benefits of the partnership project.
- On 4 September 2020 the investment project (2.7 MB )was prepared.