CONSTRUCTION AND OPERATION OF ZARASAI BYPASS ROAD

images_2019_kovas_aplinkelis.jpg


Stage: 1. Project preparation
Implementing Authority Via Lietuva
Partnership form Public-Private Partnership
Duration 25 years (3 years – reconstruction; 22 years – services)
Value 60 959 886 Eur (inc. VAT) Net Present Value
Private investment 54 827 570 Eur (inc. VAT) real value
Partner selection form Negotiated Procedure with Publication of a Contract Notice
Private partner
Contract signature date -
The date of full entry into force of the contract
Transmitted activities Road construction, repair, maintenance
Description:

The project aims to grant a private partner the right to construct a category III trunk road for transit traffic around the centre of Zarasai city (length – 9.34 km., 2 lanes), and to carry out their repair and maintenance during the period of provision of services

Area: Roads, bridges, tunnels, parking and other infrastructure of road transporte

Current situation

  • On 23 September 2025 Central Project Management Agency provided a conclusion on the PPP application.
  • In 2025 PPP project documents were prepared