Activity delegated to a pivate entity: construction; design ( infrastructure design and other necessary engineer services); services (cleaning and waste management in the teritory and premises, administration and maintenance of the developed infrastructure, maintenance of engineer systems and networks).
Maximal area of building / lot ~ 22 000 m2 / 10 ha.
The PPP contract will be signed for a period of 15 years, including around 2,5 years for developing the infrastructure and the remaining 12,5 years for operating it.
The private investor or investors will invest their own financial resources into the millitary infrastructure and will take in the construction and infrastructure operation risks.
More information about the project: https://kam.lt/en/defence_ppp.html
[[#ex]]
Current situation
- On 8 January 2024 commencement of services in military unit kas begun.
- Summary PPP Risk Assessement for inclusion in the national financial statement can be found here (214 KB ).
- On July 2020 the final stage of negotiations.
- On January 2020 the initial proposals were evaluated and the participants were invited to negotiations.
- On september 2019 completed evaluation of the application, initial proposals from candidates expected.
- On 5 March 2019 the Ministry of National Defence published procurement documents (announcement).
- On 21 January 2019 the Ministry of National Defence held the second round of public presentation and discussion for interested business representatives concerning procurement documents (public presentation (1.5 MB ) (1.5 MB )).
- On 18 December 2018 the Ministry of National Defence published procurement documents for comments and suggestions. More information: http://kam.lt/en/defence_ppp.html.
- On 27 November 2018, The Government of the Republic of Lithuania approved the decision that the project will be implemented as the Public-Private Partnership.
- On 31 October 2018 the Ministry of National Defence represented their project in Central Project Management Agency event.
- On 26 September 2018 Central Project Management Agency evaluated socio-economic benefits of the partnership project.
- On 2018 the investment project (1.7 MB ) was prepared.