Projects

PROJECT OF THE MINISTRY OF NATIONAL DEFENCE – ŠIAULIAI DISTRICT

571_b9cc14b5a94ece8417de2a9084bddc17.jpg


Stage: 4. Project implementation
Implementing Authority The Ministry of National Defence
Partnership form Public-Private Partnership
Duration 15 years
Value EUR 55,756 million (incl. VAT)
Private investment EUR 36.5 (without VAT)
Partner selection form Negotiated Procedure with Publication of a Contract Notice
Private partner UAB „Samogitia miestelis“ ir UAB „Partnerystės projektai keturi“
Contract signature date 2021 01 08
The date of full entry into force of the contract
Transmitted activities Design, construction and provision of services
Description:

Activity delegated to a pivate entity: construction; design ( infrastructure design and other necessary engineer services); services (cleaning and waste management in the teritory and premises, administration and maintenance of the developed infrastructure, maintenance of engineer systems and networks).

Maximal area of building / lot ~ 24 000 m2 / 8 ha.

The PPP contract will be signed for a period of 15 years, including around 2,5 years for developing the infrastructure and the remaining 12,5 years for operating it.

The private investor or investors will invest their own financial resources into the millitary infrastructure and will take in the construction and infrastructure operation risks.

More information about the project: https://kam.lt/en/defence_ppp.html

Area: Public order and safety

[[#ex]]

Current situation

  • Summary PPP Risk Assessement for inclusion in the national financial statement can be found here. (212 KB )
  • On July 2020 the final stage of negotiations.
  • On January 2020 the initial proposals were evaluated and the participants were invited to negotiations.
  • On september 2019 completed evaluation of the application, initial proposals from candidates expected.
  • On 5 March  2019  the Ministry of National Defence published procurement documents (announcement).
  • On 21 January  2019  the Ministry of National Defence held the second round of public presentation and discussion for interested business representatives concerning procurement documents (public presentation (1.5 MB ) (1.5 MB )).
  • On 18 December  2018  the Ministry of National Defence published procurement documents for comments and suggestions. More information: http://kam.lt/en/defence_ppp.html.
  • On 27 November 2018, The Government of the Republic of Lithuania approved the decision that the project will be implemented as the Public-Private Partnership.
  • On 31 October 2018 the Ministry of National Defence represented their project in Central Project Management Agency event.
  • On  26 September 2018 Central Project Management Agency evaluated socio-economic benefits of the partnership project.
  • On 2018 the investment project (1.7 MB ) was prepared.

[[#ex]]

Last updated: 30 01 2024