Stage: 1. Project preparation
Implementing Authority
Ministry of National Defense
Partnership form
Public-Private Partnership
Duration
15 years
Value
1 826 722 533 including VAT (In Real Value)
Private investment
1 509 850 885 including VAT (In Real Value)
Partner selection form
Private partner
Contract signature date
-
The date of full entry into force of the contract
Transmitted activities
Design, construction, maintenance, provision of public services
Description:
The Rūdninkai military town will occupy an area of about 170 hectares. It is planned to build 120 different buildings, occupying about 335 thousand square meters of territory. This military campus will be equipped with residential, administrative, sports, storage, technical buildings, transport parking lots and helipads. The military campus will be dedicated to German military forces, as well as Lithuanian soldiers.
Photo of the Ministry of National Defense/ sergeant A.Čemerka
Area:
[[#ex]]
Current situation
- On 11 December 2024 the Government of the Republic of Lithuania made a decision on the purposiveness of a PPP implementation.
- On 5 December 2024 Central Project Management Agency provided a conclusion on the PPP application.
- In 2024 November an investment project was prepared.